When "No Problem" Becomes a Change Order Problem
Two words can cost a contractor more margin than almost any line in the estimate: “no problem.” A client asks for one small extra, someone on the crew agrees on the spot, and scope, schedule and price all change without anyone writing it down. In the moment, it feels like good service. Later, it shows up as unpaid work, a slipped schedule, a frustrated sub and a client who remembers the conversation differently than you do. For small and mid-size construction businesses, these quick yeses add up fast. The fix isn’t saying no. It’s a process that turns every request into a clear, priced, signed decision.
Key Points
- A casual “no problem” can turn a small request into thousands of dollars of unpriced work. In one example from The Aspire Institute, a seemingly small add-on approved on the spot winds up costing as much as $7,200.
- Verbal approvals made under schedule pressure are a common root of change order disputes.
- The goal isn’t zero change orders. It’s changes that are planned, priced and approved before the work happens.
- Clients should hear how changes work before they sign, and everyone on site should know how to respond to a request.
- Agree on the change process in the contract, before work begins.
Why Does “No Problem” Cost So Much?
In 7 Profit Leaks that Start Before Construction Does, The Aspire Institute walks through a familiar scenario. An owner asks a crew member for a small add-on, and the answer on the spot is “no problem.” The next trade shows up without the materials the extra work needs and has to leave, so a day is lost. Once a backordered part pushes the job back a week, Aspire puts the true price of that favor as high as $7,200.
Aspire also cautions against counting on change orders for profit. The schedule hit to the current job, and to every job lined up after it, usually costs more than the markup brings in.
The bigger risk is a dispute. In Colonial Surety Company’s blog What Did You Say? Change Order Disputes!, Spencer Krebs, writing for Construction Dive, notes that when issues come up mid-job, the push to keep moving often means a nod or a quick phone call stands in for sign-off. Changed work done without written approval is a frequent source of lawsuits.
How Can Contractors Avoid the Costs of “No Problem”?
Client communication
- Explain the change process early and often. Aspire suggests introducing it in your proposal, expanding on it during preconstruction, and walking through it again at signing. Having the client initial that clause helps it stick.
- Give the whole crew one answer. Every person on site should know to say something like: “Good question. I’ll have our project manager reach out to you about it.”
- Confirm every conversation in writing. After talking with a client, send a short email summarizing what was agreed and ask them to reply to confirm or correct it.
Contract terms
- Agree on the process before anyone signs. In Colonial Surety Company’s blog Before The Shovel Hits The Dirt…, Dan Feinblum of HKA Global makes the case that change is a certainty on any build, and planning for it starts with admitting that. Spell out how changes are requested, priced, documented and approved.
- Plan for urgent changes. Krebs recommends a fallback approval path for urgent changes, so the job can keep moving without relying on a handshake.
- Check the contract before doing changed work. Know what your contract requires, from paperwork to deadlines to who signs. A short pause now is cheaper than a fight at closeout.
- Connect the office and the field. Share the key change and notice clauses with the people building the job, and lean on a strong project manager to keep owners, subs and suppliers informed.
Protect Your Margins, Then Bid Bigger
Disciplined change management protects your profit and builds the track record that bonded work depends on. Colonial Surety Company offers two bonding programs to help small and mid-size contractors take the next step.
- The Hometown Bonding Program is built for local contractors who are new to bonding or need bid and performance bonds only occasionally. Underwriting is credit based, and the program is designed to help you grow into a surety line of credit.
- The Partnership Account® for Contractors lets seasoned contractors pre-qualify for a surety line of credit of up to $20 million single and $40 million aggregate. Once approved, you can issue your own bid bonds and order performance and payment bonds online, with direct access to an underwriter when you need one.
Founded in 1930, Colonial Surety Company is rated “A” (Excellent) by A.M. Best and is U.S. Treasury listed. Explore our bonding programs and find the one that fits where your business is today.
Helpful Resources
Frequently asked questions